Construction Schedule:
Commence Construction & Drawdown of Reservoir – Nov 2016
Achieve Milestone 1 & Partial Refill of Reservoir – April 2017
Substantial Completion & Full Refill of Reservoir – Oct 2018
Final Restoration – December 2018